Currently, many of the district trail access points, lack such things as basic directional signs, information kiosks, infrastructure, or clearly defined parking. Resource impacts have been identified, so proposal is begin implementing improvements.
Location
various trailheads on the Silver City Ranger District
Project timeline
1
Scoping Start
01/13/2020
2
Decision
08/2020 (Estimated)
3
Implementation
10/2020 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (1), 36 Cfr 220.6(E)(1) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Developed Site Management; Trail Management |
| Phase 1: Pinos Altos Trailhead/Day Use Areas Improvements | Decision Signed Date: 08/31/2020 |
| Forests | Gila National Forest |
| Districts | Silver City Ranger District |
| Legal Land Description | Turkey Crk T14S R16W S21; Bear Mtn T17S R15W S1; NF Walnut T16S R14W S31, Little Walnut T17S R14W S3; Bear Crk T16S R13W S30; Signal Pk/Meadow Crk T16S R13W S4,9 |