Issue a Special Use Permit for installation of fiber optic line attached to existing utility line infrastructure in Sierra County, NM
Location
Line runs east to west for a approximately 1 mile to the community of Kingston, NM
Project timeline
1
Scoping Start
12/07/2021
2
Decision
03/2022 (Estimated)
3
Implementation
06/2022 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Sacred Wind Fiber Optics Special Use Permit Issuance | Decision Signed Date: 03/25/2022 |
| Forests | Gila National Forest |
| Districts | Black Range Ranger District |
| Legal Land Description | T16S R8W Sec. 17 and 18 |