Decision Memo Completed

Tucson Electric Power Company Permit Reissuance

Gila National Forest Catron, New Mexico Gila National Forest All Units

Reissue as one master special use permit, the individual permits for utility corridor access and maintenance for two transmission lines in Quemado, Glenwood and Reserve.

Location

Utility line cooridor extends from forest boundary on Quemado RD south to the Reserve RD and Glenwood RD crossing into Arizona near the San Francisco River

Project timeline

1
Scoping Start
03/24/2023
2
Decision
10/2023 (Estimated)
3
Implementation
12/2023 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.12 (11), 36 Cfr 220.6(D)(11)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityElectric Transmission; Special Use Authorizations
Tucson Electric Power Company Master Special Use Permit (MSUP)Decision Signed Date: 10/31/2023
ForestsGila National Forest
DistrictsQuemado Ranger District; Glenwood Ranger District; Reserve Ranger District
Legal Land DescriptionNot Applicable
Special use management