Issue a special use permit for the access and maintenance of the existing WS Ditch (i.e. ditch, sand traps, and pipeline)
Location
Project is located approximately 7 miles north of Glenwood, NM
Project timeline
1
Scoping Start
02/02/2024
2
Decision
02/2024 (Estimated)
3
Implementation
02/2024 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Phyllis McKeen (WS Ditch) Special Use Permit | Decision Signed Date: 02/21/2024 |
| Forests | Gila National Forest |
| Districts | Glenwood Ranger District |
| Legal Land Description | T10S R20W SECTION 29 |