Installation of a collector, fixed to a metal frame with a base of cinder blocks approximately 2x2 feet in size to collect precipitation event data.
Location
Site is located off of FSR 970; east of the Gila Cliff Dwellings visitor center
Project timeline
1
Scoping Start
03/25/2025
2
Decision
05/2025 (Estimated)
3
Implementation
05/2025 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| USGS Precipitation Collector Site | Decision Signed Date: 05/20/2025 |
| Forests | Gila National Forest |
| Districts | Wilderness Ranger District |
| Legal Land Description | T12S R14W Sec 25 |