Re-issue a 400' x 5' right-of-way easement for a water conveyance system. This re-issuance includes a two spring development, buried pipeline and a wildlife water trough.

Location

East of Chippaway Park about 1.5 miles and north of Hwy 130.

Project timeline

1
Scoping Start
12/20/2007
2
Decision
11/2010 (Estimated)
3
Implementation
01/2011 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (15)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
Charles P. Fuller and Lois Fuller Water Transmission PipelineDecision Signed Date: 11/17/2010
ForestsLincoln National Forest
DistrictsSacramento Ranger District
Legal Land DescriptionNw1/4, Sw1/4 of Sec 14, T. 16 S., R. 12 E, NMPM