1
Scoping Start
07/20/2011
2
Comment Period
05/17/2012
3
Decision
08/2012 (Estimated)
4
Implementation
08/2012 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivitySpecial Use Authorizations
U.S. Customs and Border Projection Modifications of Comm Equip and FaclDecision Signed Date: 08/02/2012 Legal Notice Date: 08/02/2012
ForestsLincoln National Forest
DistrictsGuadalupe Ranger District
Legal Land DescriptionT25S, R22E, Section 31
Special use management