Authorize upgrades to a 3.4-mile distribution line crossing NFS lands.
Location
Cora Dutton Road (Forest Road 488)
Project timeline
1
Scoping Start
01/16/2013
2
Comment Period
01/16/2013
3
Decision
07/2013 (Estimated)
4
Implementation
08/2013 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Special Use Authorizations |
| Cora Dutton Power Line Reconstruction | Decision Signed Date: 07/10/2013 Legal Notice Date: 07/17/2013 |
| Forests | Lincoln National Forest |
| Districts | Smokey Bear Ranger District |
| Legal Land Description | T. 9 S., R. 13 E., sec. 13, 23, and 24 |