Construct approximately 300 feet of primary overhead line, and 2 new poles with guy wires to supply power to operate a well that supplies water for livestock and wildlife on a grazing allotment.
Location
Scott Able Allotment
Project timeline
1
Scoping Start
02/01/2018
2
Decision
03/2018 (Estimated)
3
Implementation
03/2018 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Otero County Electric Cooperative Range Powerline | Decision Signed Date: 03/02/2018 |
| Forests | Lincoln National Forest |
| Districts | Sacramento Ranger District |
| Legal Land Description | T. 18 S., R. 12 E.; Section 21 |