Part 1- construct 13.51 miles of 4 primitive trails from the tip of the Switchback trail to the Fresnal Road. This project originally included Part 2 and Part 3. Part 2 is on hold and a new separate project number was created for Part 3 #59470.
Location
Fresnal Canyon area
Project timeline
1
Scoping Start
09/26/2018
2
Decision
10/2018 (Estimated)
3
Implementation
11/2018 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (1), 36 Cfr 220.6(E)(1) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Trail Management |
| Rails to Trails Trail Project Part 1 | Decision Signed Date: 10/23/2018 |
| Forests | Lincoln National Forest |
| Districts | Sacramento Ranger District |
| Legal Land Description | Not Applicable |