Reconstruction of 3 miles of pipeline and the repair of a preexisting spring diversion to provide waters to wildlife and livestock. See "other project information" for additional project description.
Location
The legal location is at Sections 4, 5, 8, and 9 of Township 8 South /Range 17 East and Section 33 of Township 7 South /Range 17 East.
Project timeline
1
Scoping Start
04/17/2018
2
Decision
06/2018 (Estimated)
3
Implementation
06/2018 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Species Habitat Improvements |
| Copeland Canyon Pipeline Reconstruction Project | Decision Signed Date: 06/04/2018 |
| Forests | Lincoln National Forest |
| Districts | Smokey Bear Ranger District |
| Legal Land Description | The legal location is at Sections 4, 5, 8, and 9 of Township 8 South /Range 17 East and Section 33 of Township 7 South /Range 17 East. |