Issuance of a new 30-year permit to Bell Ranch Joint Venture for continued operations and maintenance of a spring development and water transmission line.
Location
12 miles south of High Rolls, New Mexico.
Project timeline
1
Scoping Start
03/16/2020
2
Decision
06/2020 (Estimated)
3
Implementation
06/2020 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (15) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Domes Water Transmission Permit Reissue | Decision Signed Date: 06/22/2020 |
| Forests | Lincoln National Forest |
| Districts | Sacramento Ranger District |
| Legal Land Description | Not Applicable |