Reopen 6 existing gravel pits across the Forest for admin use to excavate, crush and stockpile rock for future road maintenance; 1 pit on the Smokey Bear RD, 2 on the Sacramento Ranger RD and 3 on the Guadalupe RD. Excavation to be completed in 1 yr.
Location
1 pit on the Smokey Bear RD, 2 on the Sacramento Ranger RD and 3 on the Guadalupe RD. See maps for specific location of each gravel pit.
Project timeline
1
Scoping Start
03/16/2021
2
Decision
08/2021 (Estimated)
3
Implementation
08/2021 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (8), 36 Cfr 220.6(E)(8) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Minerals Or Geology Plans Of Operations |
| Reopen Gravel Pits for Administrative Use | Decision Signed Date: 08/10/2021 |
| Forests | Lincoln National Forest |
| Districts | Lincoln National Forest All Units |
| Legal Land Description | Not Applicable |