Proposing to (1) construct a new trailhead, (2) reclaim a user-created parking lot, (3) construct a new trail bridge, (4) construct a new parking area on the west side of Cedar Creek Drive, and (5) construct trails within the Cedar Creek area.
Location
Cedar Creek Trail System immediately west of Ruidoso, New Mexico.
Project timeline
1
Scoping Start
09/13/2022
2
Decision
12/2022 (Estimated)
3
Implementation
03/2023 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (1), 36 Cfr 220.6(E)(1); 32.2 (18), 36 Cfr 220.6(E)(18); 32.2 (20), 36 Cfr 220.6(E)(20); 32.2 (22), 36 Cfr 220.6(E)(22) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Developed Site Management; Trail Management |
| Cedar Creek Trailheads, Bridge, and Trail Construction 2022 | Decision Signed Date: 12/12/2022 |
| Forests | Lincoln National Forest |
| Districts | Smokey Bear Ranger District |
| Legal Land Description | Sections 9 and 16 of T. 11 S., R. 13 E., NMPM |