Village of Ruidoso proposes to expand an existing building which houses water monitoring equipment in the North Fork Eagle Creek wellfield. The 7.3' x 7.3' building would double in size. Total surface disturbance would be less than 0.5 acres.
Location
North Fork Eagle Creek drainage along FS Road 127A approximately 4 miles northwest of Ruidoso, New Mexico.
Project timeline
1
Scoping Start
12/07/2022
2
Decision
01/2023 (Estimated)
3
Implementation
01/2023 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| North Fork Eagle Creek Wells Control Building Expansion | Decision Signed Date: 01/13/2023 |
| Forests | Lincoln National Forest |
| Districts | Smokey Bear Ranger District |
| Legal Land Description | Section 36 of T. 10 S., R. 12 E., NMPM |