Reconstruction of six existing water catchments and one new water catchment.
Location
Black Mesa area and Pine Mountain area
Project timeline
1
Scoping Start
09/01/2009
2
Comment Period
12/27/2012
3
Decision
07/2013 (Estimated)
4
Implementation
09/2013 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Species Habitat Improvements |
| Big Black Mesa Wildlife Water Development Projects | Decision Signed Date: 07/31/2013 |
| Forests | Prescott National Forest |
| Districts | Chino Valley Ranger District; Verde Ranger District |
| Legal Land Description | T 18-19 N, R 2-3 W; T 17 N, R 6 W |