The Forest Service proposes to issue a permit for the Poland Junction Substation. The substation was previously permitted in conjunction with the Childs 69kV subtansmission line.
Location
Approximately 10 miles southeast of the city of Prescott of FR 667.
Project timeline
1
Scoping Start
08/09/2010
2
Decision
10/2010 (Estimated)
3
Implementation
12/2010 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Poland Junction Substation 50-year Permit | Decision Signed Date: 10/29/2010 |
| Forests | Prescott National Forest |
| Districts | Bradshaw Ranger District |
| Legal Land Description | T12N, R1E, SE ¼ of the NE ¼ of Section 5 |