The Forest Service is proposing to issue a permit to Arizona Public Service to rebuild an existing 12 kV overhead primary power line that feeds Ponderosa Park subdivision.
Location
Along Ponderoasa Road to Ponderosa Park subdivision
Project timeline
1
Scoping Start
09/12/2011
2
Decision
10/2011 (Estimated)
3
Implementation
11/2011 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| White Spar 12kV Distribution Line Rebuild Phase II | Decision Signed Date: 10/09/2011 |
| Forests | Prescott National Forest |
| Districts | Bradshaw Ranger District |
| Legal Land Description | East ½ sec. 20, North ½ sec. 29; T. 13 N., R. 2 W., G&SRM |