The Forest Service is proposing to issue a permit to Arizona Public Service to install an underground power line to supply the Gray Wolf Regional Landfill. This underground power line will be within an ADOT right-of-way for State Highway 169.
Location
Along the south side of State Highway 169 from Orme Road to the private land at the Gray Wolf Regional Landfill.
Project timeline
1
Scoping Start
12/19/2011
2
Comment Period
05/31/2012
3
Decision
07/2012 (Estimated)
4
Implementation
01/2013 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Special Use Authorizations |
| APS Gray Wolf/Waste Management 12 kV Power Line | Decision Signed Date: 07/03/2012 Legal Notice Date: 07/12/2012 |
| Forests | Prescott National Forest |
| Districts | Verde Ranger District |
| Legal Land Description | G&SRM T. 13 N., R. 2 E., secs. 3, 4, 10, 11, 12; T. 13 N., R. 3 W., secs. 7and 8. |