The Forest Service is proposing to authorize the owner of the Friendly Pines Organization Camp to install underground electrical utility lines for approximatley 425 linear feet from an electrical panel in front of the infirmary to the feed barn.
Location
Camp Friendly Pines on Frienly Pines Road about 1 mile west of Senator HIghway in Groom Creek
Project timeline
1
Scoping Start
07/02/2012
2
Comment Period
07/06/2012
3
Decision
09/2012 (Estimated)
4
Implementation
09/2012 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Special Use Authorizations |
| Friendly Pines Organization Camp Underground Electric Line | Decision Signed Date: 09/05/2012 Legal Notice Date: 10/05/2012 |
| Forests | Prescott National Forest |
| Districts | Bradshaw Ranger District |
| Legal Land Description | R2W, T12.5N, Sect 27 |