The Prescott National Forest proposes to reissue an existing priority special use permit for outfitting and guiding (Hunting) for a period of 10 years.Guided hunting activities can occur year round, but are primarily in the fall hunt seasons.
Location
The proposed activities are for the entire Prescott Forest including eight wilderness areas.
Project timeline
1
Scoping Start
09/05/2014
2
Decision
09/2015 (Estimated)
3
Implementation
01/2016 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (15) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Dispersed Recreation Mgmt.; Special Use Authorizations |
| Hunting Outfitter Guide Priority Special Use Permit | Decision Signed Date: 09/15/2015 |
| Forests | Prescott National Forest |
| Districts | Prescott National Forest All Units |