Environmental Assessment Cancelled

Eastside Ore Reserve - Gold Basin Supplement

Prescott National Forest Yavapai, Arizona Prescott National Forest All Units

This project would include placer gold mining operations on approximately 6 acres of land. Mining activities include mining out two deposits (Pit # 3 and # 4), developing an access road off FR 9262E, and a stockpile site. This is a 15-year project.

Location

This project is located east of the Gold Basin Mine south of Wilhoit along the Hassayampa River.

Project timeline

1
Scoping Start
11/03/2014
2
Comment Period
02/2016 (Estimated)
3
Objection Period Start
07/2016 (Estimated)
4
Decision
09/2016 (Estimated)
5
Implementation
10/2016 (Estimated)

NEPA / regulatory detail

Special AuthorityNot Applicable / Other
Notice and Comment Regulation218 (2013) Non-HFRA
Project ActivityMinerals Or Geology Plans Of Operations
ForestsPrescott National Forest
DistrictsBradshaw Ranger District
Legal Land DescriptionT 12 N, R 3 W, Section 11
Minerals and geology