Receration improvements including campground host site development, trailhead development, and toilet facility installation.
Location
Santa Fe National Forest
Project timeline
1
Scoping Start
09/15/2009
2
Comment Period
11/13/2009
3
Decision
12/2009 (Estimated)
4
Implementation
06/2010 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Developed Site Management; Facility Improvements/Construction |
| Forest-wide Recreation Improvement Project Rio De Las Vacas Campground | Decision Signed Date: 12/18/2009 Legal Notice Date: 12/29/2009 |
| Forest-wide Rec. Imp. E.V. Long, El Porvenir, and Holy Ghost Campgrounds | Decision Signed Date: 12/21/2009 Legal Notice Date: 12/29/2009 |
| Forest-wide Rec Imp Proj - Whirlpool Site, and NS Plan Amendment | Decision Signed Date: 12/21/2009 Legal Notice Date: 12/29/2009 |
| Forests | Santa Fe National Forest |
| Districts | Santa Fe National Forest All Units |