The project would permit construction and maintenance of a buried power line and fiber optic line in the same trench, about 3.3 miles, between Nichols Dam eastward to McClure Dam.
Location
East of the City of Santa Fe, near the City water treatment plant, within the Santa Fe Municipal Watershed.
Project timeline
1
Scoping Start
10/26/2017
2
Decision
08/2018 (Estimated)
3
Implementation
09/2018 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| City of Santa Fe Electrical and Fiber Optic Line Project | Decision Signed Date: 08/23/2018 |
| Forests | Santa Fe National Forest |
| Districts | Espanola Ranger District |
| Legal Land Description | Not Applicable |