Environmental Assessment Completed

Camp May Water Pipeline Project

Santa Fe National Forest Los Alamos, New Mexico Espanola Ranger District

Installation of an underground water pipeline and pump stations from West Road to Pajarito Ski Area along the ski hill road for snow making and fire response. Includes a new water tank adjacent to the existing Tank along West Road on DOE land

Location

Water Pipeline up Ski Hill Road to the Pajarito Ski Area

Project timeline

1
Scoping Start
02/14/2018
2
Comment Period
05/20/2020
3
Objection Period Start
12/02/2021
4
Decision
03/2022 (Estimated)
5
Implementation
03/2022 (Estimated)

NEPA / regulatory detail

Special AuthorityNot Applicable / Other
Notice and Comment Regulation218 (2013) Non-HFRA
Project ActivitySpecial Use Authorizations
Camp May Water Pipeline ProjectDecision Signed Date: 03/01/2022
ForestsSanta Fe National Forest
DistrictsEspanola Ranger District
Legal Land DescriptionNot Applicable
Special use management