Installation of an underground water pipeline and pump stations from West Road to Pajarito Ski Area along the ski hill road for snow making and fire response. Includes a new water tank adjacent to the existing Tank along West Road on DOE land
Location
Water Pipeline up Ski Hill Road to the Pajarito Ski Area
Project timeline
1
Scoping Start
02/14/2018
2
Comment Period
05/20/2020
3
Objection Period Start
12/02/2021
4
Decision
03/2022 (Estimated)
5
Implementation
03/2022 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Special Use Authorizations |
| Camp May Water Pipeline Project | Decision Signed Date: 03/01/2022 |
| Forests | Santa Fe National Forest |
| Districts | Espanola Ranger District |
| Legal Land Description | Not Applicable |