To replace the existing 5 pit toilets at Redondo Campground and the 1 pit toilet at East Fork Trailhead with vault toilets.
Location
Redondo Campground and East Fork Trailhead
Project timeline
1
Scoping Start
05/17/2019
2
Decision
11/2019 (Estimated)
3
Implementation
02/2020 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (3), 36 Cfr 220.6(D)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Developed Site Management |
| Redondo Campground and East Fork Trailhead Toilet Demolition and Replacement Project | Decision Signed Date: 11/13/2019 |
| Forests | Santa Fe National Forest |
| Districts | Jemez Ranger District |
| Legal Land Description | Not Applicable |