Decision Memo Completed

Tesuque Peak Powerline Rebuild

Santa Fe National Forest Santa Fe, New Mexico Santa Fe National Forest All Units

Jemez Mountain Electric Coop, proposed to Repair and Replace numerous wooden poles, cross bars and conductor. From the boundary of Pueblo of Nambe to the Santa Fe Ski area.

Location

Jemez Mountains Electric Coop Right-of-Way thru SFNF lands that supply power to Santa Fe Ski and Tesuque Commnication site. This ROW is 5.5 mi long, running from Nambe to Santa Fe Ski.

Project timeline

1
Scoping Start
08/01/2023
2
Decision
11/2023 (Estimated)
3
Implementation
11/2023 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (2), 36 Cfr 220.6(E)(2)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityElectric Transmission; Special Use Authorizations; Facility Maintenance
Tesuque Peak Powerline Emergency RebuildDecision Signed Date: 11/06/2023
ForestsSanta Fe National Forest
DistrictsEspanola Ranger District
Legal Land DescriptionNot Applicable
Special use management