Decision Memo Completed

Ski Santa Fe Chairlift 4 In-line Replacement

Santa Fe National Forest Santa Fe, New Mexico Santa Fe National Forest All Units

The project is needed to upgrade declining infrastructure, ensuring efficient operations and improve user satisfaction. The existing Chair 4 infrastructure will be replaced with Chair 1 infrastructure.

Location

Santa Fe Ski Basin

Project timeline

1
Scoping Start
05/28/2024
2
Decision
10/2024 (Estimated)
3
Implementation
10/2024 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (22), 36 Cfr 220.6(E)(22)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityDeveloped Site Management
Ski Santa Fe Chairlift 4 In-line ReplacementDecision Signed Date: 10/22/2024
ForestsSanta Fe National Forest
DistrictsEspanola Ranger District
Legal Land DescriptionTownship 18N, Range 11E, Section 8
Recreation management