Decision Memo Completed

Chamberlain Pit

Tonto National Forest Gila, Arizona Pleasant Valley Ranger District

The Chamberlain Pit will be used to supply approximately 2,000 cubic yards of DG material for the Haigler Canyon Recreation Site CIP project. This will involve moving one power pole and terracing the pit for disperse camping use in the future.

Location

Intersection of FR 200 and FR 848

Project timeline

1
Scoping Start
01/09/2006
2
Decision
08/2006 (Estimated)
3
Implementation
04/2006 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (8), 36 Cfr 220.6(E)(8)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityMinerals Or Geology Plans Of Operations
Chamberlain Pit Decision MemoDecision Signed Date: 08/18/2006
ForestsTonto National Forest
DistrictsPleasant Valley Ranger District
Minerals and geology