The Chamberlain Pit will be used to supply approximately 2,000 cubic yards of DG material for the Haigler Canyon Recreation Site CIP project. This will involve moving one power pole and terracing the pit for disperse camping use in the future.
Location
Intersection of FR 200 and FR 848
Project timeline
1
Scoping Start
01/09/2006
2
Decision
08/2006 (Estimated)
3
Implementation
04/2006 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (8), 36 Cfr 220.6(E)(8) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Minerals Or Geology Plans Of Operations |
| Chamberlain Pit Decision Memo | Decision Signed Date: 08/18/2006 |
| Forests | Tonto National Forest |
| Districts | Pleasant Valley Ranger District |