Environmental Assessment Completed

APS Mazatzal 345 Kv Substation

Tonto National Forest Gila, Arizona Tonto Basin Ranger District

Issue a new permit to APS authorizing the construction and operation of a 21-acre substation near Rye, AZ

Location

South of Payson near Rye, AZ

Project timeline

1
Scoping Start
02/05/2008
2
Comment Period
06/25/2010
3
Decision
08/2010 (Estimated)
4
Implementation
01/2011 (Estimated)

NEPA / regulatory detail

Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivitySpecial Use Authorizations
ARIZONA PUBLIC SERVICE MAZATZAL 345/69/21KV SUBSTATIONDecision Signed Date: 08/24/2010 Legal Notice Date: 08/27/2010
ForestsTonto National Forest
DistrictsTonto National Forest All Units
Legal Land DescriptionT 8 N, R 10 E, Section 4, GSRM
Special use management