Construction of Cellular facility adjacent to the Goldfield administrative site on the Lower Salt River. A relay facility will be constructed on Stewart Mountain and equipment added to existing facility at Saguaro Lake Marina.
Location
Adjacent to Goldfield Administrative Site, Stewart Mountain near existing passive reflector.
Project timeline
1
Scoping Start
06/21/2012
2
Comment Period
05/03/2013
3
Decision
07/2013 (Estimated)
4
Implementation
08/2013 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Special Use Authorizations |
| Goldfield-Stewart Mountain Communications Facilities | Decision Signed Date: 07/22/2013 Legal Notice Date: 08/02/2013 |
| Forests | Tonto National Forest |
| Districts | Mesa Ranger District |
| Legal Land Description | GSRM T.3.N R.7.E Sec. 34 |