Reissue a permit to maintain & operate an existing telephone/telegraph line (Magma Signal Line). Originally authorized in 1969 (Magma Arizona Railroad). Purpose of line is to monitor & control of water pumps.
Location
NW1/4, Sec. 4, T.2S, R.12E to SW1/4, Sec. 6, T.2S, R.11E., G.S.R.B. & M.
Project timeline
1
Scoping Start
05/25/2012
2
Comment Period
05/25/2012
3
Decision
07/2012 (Estimated)
4
Implementation
08/2012 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (15) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Special Use Authorizations |
| AZ Water Company Transmission Lines Permit Reissuances | Decision Signed Date: 07/31/2012 Legal Notice Date: 08/17/2012 |
| Forests | Tonto National Forest |
| Districts | Globe Ranger District |
| Legal Land Description | NW1/4, Sec. 4, T.2S, R.12E to SW1/4, Sec. 6, T.2S, R.11E., G.S.R.B. & M. |