Reissue permit to maintain and operate a 12 inch diameter water transmission main from private wells to the Town of Superior within a 10 foot wide by 9.53 mile long ROW. To include 2" spur service line. This waterline has been authorized since 1969.
Location
Sec. 32, 33, 34, 35 in T.1S., R.11E. and Sec. 1, 2, 3, 6 in T.2S., R311E., and Sec. 4, 5, 6 in T.2S., R.12E., G.S.R.B.&M., Pinal Count, AZ
Project timeline
1
Scoping Start
05/25/2012
2
Comment Period
05/25/2012
3
Decision
07/2012 (Estimated)
4
Implementation
08/2012 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (15) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Special Use Authorizations |
| AZ Water Co Water Transmission Lines Permit Reissuances | Decision Signed Date: 07/31/2012 Legal Notice Date: 08/17/2012 |
| Forests | Tonto National Forest |
| Districts | Globe Ranger District |
| Legal Land Description | Sec. 32, 33, 34, 35 in T.1S., R.11E. and Sec. 1, 2, 3, 6 in T.2S., R311E., and Sec. 4, 5, 6 in T.2S., R.12E., G.S.R.B.&M., Pinal Count, AZ |