Two storage tanks with mounted solar panels and pumps are proposed to be constructed next to an existing pipeline on the Dutchwoman Allotment. This will convert the existing water system into a solar operated system.
Location
Tonto Basin Ranger District, Dutchwoman Allotment
Project timeline
1
Scoping Start
05/11/2012
2
Comment Period
05/11/2012
3
Decision
06/2012 (Estimated)
4
Implementation
07/2012 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (9), 36 Cfr 220.6(E)(9) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Grazing Allotment Management |
| Cloverleaf Storage Additions Decision Memo | Decision Signed Date: 06/21/2012 Legal Notice Date: 07/03/2012 |
| Forests | Tonto National Forest |
| Districts | Tonto Basin Ranger District |
| Legal Land Description | T5N, R13E, Sec 30 |