Replacement of five gates at Bulldog OHV access points; local transplant of desert scrub and cactus to rehabilitate portions of unauthorized routes and areas leading off Forest Designated Roads (FDR) 402, 143, 401, and 10; and installation of metal r
Location
Tonto National Forest, Mesa Ranger District
Project timeline
1
Scoping Start
05/11/2012
2
Comment Period
05/11/2012
3
Objection Period Start
05/11/2012
4
Decision
06/2012 (Estimated)
5
Implementation
11/2012 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (4), 36 Cfr 220.6(D)(4); 32.12 (5), 36 Cfr 220.6(D)(5); 32.2 (5), 36 Cfr 220.6(E)(5) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 219 (2012) |
| Project Activity | Dispersed Recreation Mgmt. |
| Revegetation, Metal Rail, and Gate Replacement Project | Decision Signed Date: 06/19/2012 |
| Forests | Tonto National Forest |
| Districts | Mesa Ranger District |
| Legal Land Description | T4N, R9E, Sections 19, 23, 24, 25, 26, 30 |