Consolidates previous Plan of Operation and Special Use Permit authorizations, including continued operation of existing sedimentation basin; Use of segments of Forest Roads 229, 989, and 2403 for hauling; and mining at two unpatented claims.
Location
Superior, Arizona
Project timeline
1
Scoping Start
12/03/2013
2
Comment Period
01/14/2015
3
Objection Period Start
07/15/2015
4
Decision
07/2015 (Estimated)
5
Implementation
10/2015 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Minerals Or Geology Plans Of Operations |
| IMERYS Perlite Mine, USA Inc. Project Plan of Operations | Decision Signed Date: 07/15/2015 |
| Forests | Tonto National Forest |
| Districts | Globe Ranger District |
| Legal Land Description | Township 2 South, Range 12 East, Sections 4 and 9 |