The Arizona Department of Transportation has proposed to reopen and expand the existing Fish Creek Mineral Material borrow pit to obtain mineral materials necessary for the maintenance of State Route 88.
Location
Located approximately 12 miles southwest of Roosevelt Lake along State Route 88.
Project timeline
1
Scoping Start
01/07/2015
2
Decision
07/2015 (Estimated)
3
Implementation
08/2016 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Minerals Or Geology Plans Of Operations |
| Fish Creek Mineral Material Borrow Source | Decision Signed Date: 07/01/2015 |
| Forests | Tonto National Forest |
| Districts | Mesa Ranger District |
| Legal Land Description | Section 5, Township 2 North, Range 11 East, Gila and Salt River Meridan |