Issuance of a permit to replace the expired Federal Energy Regulatory Commission Hydropower License. Existing 69 kV line that was part of the Childs Irving Power operation and covered under the old license. Has been in continuous operation.
Location
Line that travels from Childs substation to Irving power plant area. Includes small sections of the Tonto NF where it crosses Fossil Creek.
Project timeline
1
Scoping Start
08/12/2015
2
Decision
08/2023 (Estimated)
3
Implementation
08/2023 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (10) |
| Special Authority | Forest Service Energy Implementation Plan |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Electric Transmission; Special Use Authorizations |
| Forests | Coconino National Forest; Tonto National Forest |
| Districts | Red Rock Ranger District; Payson Ranger District |
| Legal Land Description | Not Applicable |