Facility improvements on multiple existing communication sites. Improvements may include tower and/or structure construction, demolition, back up power replacement, photovoltaic systems, grading, surfacing, and fencing.
Location
Mt Ord, Pinal Peak, Bartlett Lake, Canyon Lake, Bronco Butte
Project timeline
1
Scoping Start
02/23/2016
2
Decision
03/2016 (Estimated)
3
Implementation
03/2016 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Multiple Communications Sites Improvement Project | Decision Signed Date: 03/16/2016 |
| Forests | Tonto National Forest |
| Districts | Tonto National Forest All Units |
| Legal Land Description | Not Applicable |