The proposed action is to amend the existing term Special Use Permit issued to Jack D. Church, Inc. to authorize the construction and maintenance of a Cable Park System within the existing Bartlett Lake Marina permit boundary.
Location
The project is located at Bartlett Lake, just off Bartlett Dam Road, approximately 11 air miles east from the Cave Creek Ranger District Office in Scottsdale, AZ.
Project timeline
1
Scoping Start
11/14/2016
2
Decision
02/2018 (Estimated)
3
Implementation
02/2018 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Developed Site Management; Special Use Authorizations |
| Decision Memo for Bartlett Lake Marina Cable Park System | Decision Signed Date: 02/22/2018 |
| Forests | Tonto National Forest |
| Districts | Cave Creek Ranger District |
| Legal Land Description | Township 6N, Range 7E, Section 28 |