The Cave Creek Ranger District proposes to install a permanent repeater site on the summit of New River Mountain to support reliable radio communications between area field personnel and the dispatch center.
Location
Project is located at the summit of New River Mountain (Township 8N, Range 3E, Section 13).
Project timeline
1
Scoping Start
03/06/2017
2
Decision
03/2017 (Estimated)
3
Implementation
05/2017 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Facility Improvements/Construction; Special Use Authorizations; Facility Maintenance |
| Decision Memo for the New River Mountain Repeater Site Project | Decision Signed Date: 03/27/2017 |
| Forests | Tonto National Forest |
| Districts | Cave Creek Ranger District |
| Legal Land Description | Not Applicable |