Placement of approximately 2200 feet of existing overhead power line underground. The existing overhead powerline has had continuous failures due to extreme ice and winds. This powerline serves numerous communication sites and Forest Service lookout.
Location
Reno Pass, Mt. Ord
Project timeline
1
Scoping Start
09/21/2017
2
Decision
10/2017 (Estimated)
3
Implementation
10/2017 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Decision Memo for APS Mt. Ord 21kV power line replacement project | Decision Signed Date: 10/16/2017 |
| Forests | Tonto National Forest |
| Districts | Tonto Basin Ranger District |
| Legal Land Description | Gila & Salt River Meridian. T. 6N., R. 9E., sec. 2, and 11. T.7N., R. 9E., sec. 34. |