Authorize following range improvements on the Cross F Allotment.
Location
Mesa Ranger District, Cross F Allotment
Project timeline
1
Scoping Start
05/11/2018
2
Decision
06/2018 (Estimated)
3
Implementation
06/2018 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (9), 36 Cfr 220.6(E)(9) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Grazing Structural Improvements |
| Mazatzal Pipelines Project | Decision Signed Date: 06/08/2018 |
| Forests | Tonto National Forest |
| Districts | Mesa Ranger District |
| Legal Land Description | Not Applicable |