a new prefab building replacing the existing, a new ice bridge with supports, a new generator and fuel tank on new slabs, trenching between the tank, generator, and building, and a new electrical trench from the building to APS transformer.
Location
Pinal Mountain Communication Site #27
Project timeline
1
Scoping Start
07/16/2019
2
Decision
10/2019 (Estimated)
3
Implementation
09/2019 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Pinal Site #27 and #29 Decision Memo | Decision Signed Date: 10/08/2019 |
| Forests | Tonto National Forest |
| Districts | Globe Ranger District |
| Legal Land Description | Township 2 South, Range 15 East, Section4 |