Project activities proposed are 13 drill sites and a temporary access road.
Location
Project would be accessed from Globe via North Arizona Highway 188, North Bixby Road, East on Forest Service Road 594, and a short stretch of temporary access road.
Project timeline
1
Scoping Start
05/25/2021
2
Decision
07/2022 (Estimated)
3
Implementation
07/2022 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (8), 36 Cfr 220.6(E)(8) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Minerals Or Geology Plans Of Operations |
| Phoenix Silver Exploration Drilling on National Forest System Lands | Decision Signed Date: 07/06/2022 |
| Forests | Tonto National Forest |
| Districts | Globe Ranger District |
| Legal Land Description | Project activities are proposed within Section 26 of Township 2 North, Range 15 East, in Gila County, Arizona |