Provide adequate handling facilities to manage livestock that are grazing allotment.
Location
The Pinto Creek Corral project is located on the Tonto Basin Ranger District. The projects is located just south of SR-188 on Forest Road 1491 on the Poison Spring Allotment.
Project timeline
1
Scoping Start
12/16/2021
2
Decision
01/2022 (Estimated)
3
Implementation
02/2022 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (9), 36 Cfr 220.6(E)(9) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Grazing Structural Improvements |
| Pinto Creek Corral | Decision Signed Date: 01/03/2022 |
| Forests | Tonto National Forest |
| Districts | Tonto Basin Ranger District |
| Legal Land Description | The legal location of the project is Township 3N, Range 13E, Section 2. |