Two new communication sites along HWY 87 will be built.
Location
Township 07N., Range 10E., Section 06 and Township 11N., Range 10E., Section 17.
Project timeline
1
Scoping Start
03/03/2025
2
Decision
04/2025 (Estimated)
3
Implementation
05/2025 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| DW Tower Callahan Communication Site | Decision Signed Date: 04/01/2025 |
| Forests | Tonto National Forest |
| Districts | Payson Ranger District |
| Legal Land Description | Not Applicable |