Implement silvicultural activities on approximately 1,200 acres in order to move affected stands toward desired vegetative conditions described in Appendix A of the Forest Plan.
Location
Spruce Creek in the Gold Fork River drainage
Project timeline
1
NOI in Federal Register
10/2013 (Estimated)
2
DEIS NOA in Federal Register
01/2014 (Estimated)
3
FEIS NOA in Federal Register
04/2014 (Estimated)
4
Objection Period Start
07/2014 (Estimated)
5
Decision
10/2014 (Estimated)
6
Implementation
06/2015 (Estimated)
NEPA / regulatory detail
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Forest Vegetation Improvements; Timber Sales (Green) |
| Forests | Boise National Forest |
| Districts | Cascade Ranger District |
| Legal Land Description | T.16N., R.5E., Section 34, etc.; Boise Meridian, Valley County, Idaho |