Implement silvicultural activities on an estimated 2,000 acres; reduce natural fuel loads on approximately 500 acres, and; decommission roughly 4 miles of road.
Location
Clear Creek drainage
Project timeline
1
NOI in Federal Register
10/13/2009
2
DEIS NOA in Federal Register
03/19/2010
3
FEIS NOA in Federal Register
07/30/2010
4
Decision
07/2010 (Estimated)
5
Implementation
10/2010 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Species Habitat Improvements; Watershed Improvements |
| Clear Prong Project Record of Decision | Decision Signed Date: 07/20/2010 Legal Notice Date: 07/26/2010 |
| Forests | Boise National Forest |
| Districts | Cascade Ranger District |
| Legal Land Description | T.14N, R.5E; T.13N, R.5E |