Issuance of a special use permit for the Idaho Department of Parks and Recreation (IDPR) to install a 20-foot diameter backcountry yurt near Beaver Creek Summit.
Location
The project located adjacent to HWY 21 near milepost 63 at the junction of HWY 21 and NFS road 551.
Project timeline
1
Scoping Start
02/01/2010
2
Decision
03/2010 (Estimated)
3
Implementation
09/2010 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Beaver Creek Yurt Installation Project | Decision Signed Date: 03/15/2010 |
| Forests | Boise National Forest |
| Districts | Idaho City Ranger District |
| Legal Land Description | T8N, R 7E, Section 21, SE 1/4, Boise Meridian |